School takes form

In the meantime it’s October and the building activities show great progress. The outlines of some of the buildings can already been seen. The first house for teaching staff has been roofed with iron sheets. For another staff house the windows has been put in place. For one of the school buildings the slabs (footing level) are ready, for another one the floor has been prepared and builders have started with building the corners.
 

 
 
 
 
 
 
 
 
 
 
 
The moulding of the Stabilized breeze blocks is an ongoing activity which is very labour- intensive. It starts with the carrying of water by some local women to the area where the clay is prepared.
After mixing the water, clay and some other ingredients, the substance is moulded in the forms and from then the sun does its work. It’s an impressive sight, this large field of bricks side by side.
Transporting of breeze-blocks from one point to another within the site is a real challenge. The project management team is investigating whether hiring a lorry would be more effective and can be done within the budget.