Second phase Luviri school started

In april the second phase of building activity started.
First two senior houses are to be built. These houses are in the last stadium of finishing, with roofing done, electrical wiring in place and plastering done.
 

 
 
 
 
 
 
At the moment work on the administration block started. Window level to beam level and next to gable level is done and preparations for roofing are made now.
 


 
 
 
 
 
 
 
 
 
 

All building activities are quite successful, delivery of materials were always in good time, which is an enormous achievement.
Furthermore labor efficiency and teamwork of the builders is very good.
On the other side the project suffered from water shortages at the project site due to some villagers deliberately breaking the main pipe to serve their cattle with water for drinking. This problem has been sorted out by engaging chiefs surrounding the villages to discuss with the communities surrounding the project area.